2 March 2012.
The final design, which takes account of local concerns, has been described as 'sensitive and elegant' |
The work is being done by contractors Alun Griffiths who expect the bridge to be complete by 2 March —and they say that the work should not cause major problems for traffic and pedestrians using the road bridge.
There are three days planned when there will be traffic light controlled lane closures in November and over two nights in mid-February the road will be completely closed and traffic diverted through Newbury and Andover.
There should be little disruption to canal traffic — but there will be restricted moorings on Hungerford Wharf.